Five proposals · July 2026

Five deck bids.
Five different scopes.

The headline prices are not apples-to-apples. This review separates the numbers from what is actually being built—so the decision comes down to structure, scope, and risk.

Important: estimates are dated July 2026. This is a comparison aid; source proposals, final contracts, and written clarifications govern.

At a glance

The decision starts with structure

Cohen and ACS retain existing upper framing/structure. Get It Rite and NexLevel rebuild it. MAT-CON appears to be a resurfacing proposal, but its framing language conflicts and needs written clarification. Only two bids include a lower dog deck.

03

Retain or repair upper structure

Cohen resurfaces existing framing. ACS replaces joists as needed. MAT-CON describes post-demo framing inspection and T&M repairs, but also says “remove…framing”; confirm the intended scope.

02

Full upper rebuild

Get It Rite and NexLevel include complete demolition and all-new upper framing.

02

Include lower deck

Cohen includes a new composite dog deck. ACS includes a 12×22 lower deck with treated or Trex Lineage composite decking.

Mobile-friendly bid cards

What each price buys

Each card leads with configuration and scope—not just the total.

Composite · two deck areas

Cohen

Upper renovation

$49,228.46

One stated configuration

Configuration

TimberTech Prime+ upper resurfacing, black TimberTech Impressions railing, new pergola, and a new lower composite dog deck with new framing.

  • IncludedJoist tape
  • IncludedLower dog deck
  • UnclearUpper framing repair allowance
  • UnclearPermits and tax
Scope caveat

The upper deck is resurfaced, not rebuilt. Confirm who absorbs hidden framing repairs after the boards come off.

Composite or treated · upper only

Get It Rite

Full rebuild

$36,947

Composite

$27,947

Treated

Configuration

Complete elevated-deck demo and rebuild with all-new treated framing; Trex Enhance Basics + Westbury on the composite option.

  • Included8 Diamond Pier footings
  • IncludedNew stairs, flashing, fascia, hardware
  • IncludedApprox. 17×12 pergola rebuild and cleanup
  • Not includedLower dog deck
  • UnclearGates, joist tape, permit and tax
Scope caveat

A strong upper-rebuild price cannot be compared directly until a lower-deck add-on and missing line items are quoted.

Composite · upper only · 430 sq ft

NexLevel

Full rebuild

$48,765.78

Includes $1,880.13 financing charge

$46,885.65 exact subtotal before financing

Configuration

Full demo/rebuild with treated substructure, TimberTech Prime+, aluminum railing, composite fascia, stairs, two gates, and 14×16 pergola.

  • Included5 helical footings
  • IncludedJoist tape and ledger flashing
  • IncludedPermits and tax
  • Not includedLower deck
Scope caveat

A $1,000 discount was valid only on the estimate date. Confirm whether it is reflected in the listed numbers; do not assume it remains available.

Trex Transcend · upper only

MAT-CON

Framing unclear

$29,539.00

Proposal dated 7/23/26 · License BC631506

Configuration

Remove old decking, handrails, and lattice; install Trex Transcend decking and black AFCO 200 Series handrails; haul away old decking and handrails; and build a new 4-foot-wide stairway with a gate at the top.

  • IncludedTrex Transcend + AFCO 200 Series
  • Included4-foot stairway and top gate
  • IncludedDecking and handrail haul-away
  • ExtraRotten framing: time + materials
  • Not includedPermit, painting, and staining
  • Not includedLower deck and lattice/pergola replacement
Scope caveat

The proposal is internally inconsistent: its opening line says remove decking, handrails, lattice “and framing,” but a later line says inspect framing after decking removal and charge only needed framing at time and materials. Treat this as resurfacing with uncertain repair exposure unless MAT-CON confirms otherwise in writing. Payments are one-third at start, one-third when decking and handrails are off, and one-third at completion.

Desktop comparison grid

Scope, line by line

Green means expressly included, gray means expressly excluded, and amber flags something conditional or not clear from the proposal.

Included Not included Unclear / conditional
Scope item
Cohen$49,228.46
ACS$50,746 composite / $37,631 / $26,450
Get It Rite$36,947 / $27,947
NexLevel$48,765.78 financed
MAT-CON$29,539 upper only
Upper approach
ResurfaceExisting framing
RetainJoists replaced as needed
Full rebuildAll-new treated framing
Full rebuild430 sq ft upper
ClarifyConflicting removal / T&M repair language
Decking / railing
TimberTech Prime+TimberTech Impressions, black
Trex Lineage or treatedWestbury, or all-treated alternative
Trex Enhance Basics or treatedWestbury on composite option
TimberTech Prime+Aluminum railing
Trex TranscendAFCO 200 Series, black
Lower dog deck
IncludedComposite, new framing
Included12×22 treated or Trex Lineage
Not included
Not included
Not included
Pergola
New pergola
$3,929 line
RebuiltApprox. 17×12
14×16
No replacement statedLattice removal only
Footings
Unclear
Evaluate only3 posts/brackets named
8 Diamond Piers
5 helical
Not stated
Stairs
Confirm scope
Included
New stairs
Included
New 4-foot stair
Joist tape
Included
Confirm
Unclear
Included
Not stated
Gates
Confirm
Confirm
Unclear
2 gates
Gate at stair top
Permits / tax
Unclear
Permit linesComposite-upper addendum: $900; confirm tax
Both unclear
Both included
Permit excludedTax not stated
Disposal / cleanup
Confirm
Disposal
Cleanup
Confirm
Decking / handrailsLattice disposal not expressly stated

On smaller screens, use the bid cards above for the same core comparison without horizontal scrolling.

Normalize before choosing

Send every contractor the same questions

Ask for written, fixed-price answers or clearly stated allowances. That turns five different proposals into a decision you can defend.

  1. 01

    Lower-deck add-on

    Price the same 12×22 lower dog deck, with the same decking, railing, stairs, gate count, framing, and footings.

  2. 02

    Permits and tax

    Are permit fees, plan review, inspections, sales tax, and any engineering costs included in the total?

  3. 03

    Gates

    How many self-closing or standard gates are included, where are they located, and what hardware is specified?

  4. 04

    Stair scope

    Confirm stair count, width, landings, railing, stringer material, lighting or code upgrades, and upper versus lower locations.

  5. 05

    Framing repairs

    For retained framing, define the included repair allowance, unit prices, approval process, and maximum exposure after demolition.

  6. 06

    Footings

    State the exact count and type, whether existing footings pass inspection, and the price if any must be replaced or upgraded.

  7. 07

    Joist tape and flashing

    Confirm joist tape coverage, ledger flashing, beam/post protection, and the exact products used.

  8. 08

    Materials and warranty

    Lock the product lines, board profiles, colors, railing series, fasteners, and manufacturer plus workmanship warranties.

  9. 09

    Payment and changes

    Provide deposit and milestone schedule, change-order markup, cancellation terms, start window, duration, and final-payment trigger.

Bottom line

Choose the construction strategy first

The “best” bid changes depending on whether the current upper structure is worth keeping.

Lowest stated two-area option if the upper structure is sound and treated materials are acceptable

ACS, treated configurations · $26,450 / $37,631

ACS’s $26,450 all-treated package is its lowest stated total for the upper work, 12×22 lower deck, and pergola. The $37,631 aluminum-rail option covers the same core areas with treated decking and adds an $11,181 premium over the all-treated package for the aluminum-railing configuration; it is $11,597.46 below Cohen. ACS also states a $50,746 Trex Lineage + Westbury package for both deck areas and the pergola—$1,517.54 above Cohen—subject to correcting the addendum’s $10 upper-total discrepancy. Every ACS choice depends on retaining the upper structure and existing footings; confirm permit, tax, stair, and disposal details for the selected configuration, and require a documented structural/footing assessment with a capped repair allowance.

02

Best rebuild value

Get It Rite · $36,947 composite

All-new framing and eight Diamond Pier footings at a compelling upper-deck price. It becomes comparable only after adding the lower deck and resolving permits, tax, gates, and joist tape.

03

Premium-material resurfacing option

MAT-CON · $29,539 upper only

Trex Transcend, black AFCO 200 Series railing, a new 4-foot stair, and a top gate are attractive at this price, but there is no lower deck or replacement pergola/lattice. Resolve the proposal’s contradictory framing language, cap time-and-materials repair exposure, and add permit cost before comparing it with fixed-scope bids.

04

Most specified upper-only rebuild

NexLevel · $46,885.65 before financing

The clearest upper-only scope: full rebuild, helical footings, protection details, gates, permits, and tax. Remove the $1,880.13 financing charge when comparing base construction cost; still add a lower-deck quote.

05

Composite two-area package

Cohen · $49,228.46

Covers both deck areas with composite and a new pergola, but keeps the existing upper framing. It is $1,517.54 below ACS’s stated Trex Lineage + Westbury composite package; the product lines and exact lower-deck scope still need normalization. Get firm language on repair exposure, footings, stairs, permits, and tax.

Recommended next move

Request one normalized revision from each bidder.

Use the nine questions above and require a final total for the same upper deck, 12×22 lower dog deck, pergola, stairs, gates, permits, tax, disposal, and footing strategy. Then compare the revised contracts—not today’s headlines.